Brandon Waste Water Treatment Plant
Building the initial wastewater treatment plant in 1999, Stuart Olson Dominion is nearing completion of a $10 million upgrade and expansion of the facility. The project has involved 50% concrete work, including construction of three bio-reactors, and 50% installation work involving mechanical, electrical, instrumentation and control systems. To meet the construction deadline, we erected a temporary structure over the project that was 60 feet wide, 250 feet long and 28 feet high, to enable construction to continue during the winter season.